The certification process: from application to certificate

The certification process follows ISO/IEC 17021-1: the application and initial audit lead to the certification decision, which starts a three-year cycle of surveillance and recertification.

Basis

ISO/IEC 17021-1

Requirements for certification bodies

Cycle

Three years

From the certification decision

Initial audit

Stage 1 and stage 2

Followed by annual surveillance

Accreditation

ISO/IEC 27001

DANAK accredited

Overview of the certification cycle

This page describes the certification process that Dansk Audit Institut (DAI) applies for management system standards. It is based on ISO/IEC 17021-1, which sets out requirements for certification bodies that audit and certify management systems. For ISO/IEC 27001, ISO/IEC 27006-1:2024 also applies.

Certification is structured as a three-year cycle. The first cycle begins with the certification decision. DAI prepares an audit programme for the full cycle so that all requirements of the standard are assessed during the period.

YearActivity
Year 0Stage 1, stage 2 and the certification decision. The certificate is issued for three years.
Year 1First surveillance audit, no later than 12 months after the certification decision
Year 2Second surveillance audit
Year 3Recertification audit before the certificate expires

The cycle then repeats. The standard pages show the process in five main steps. The full process is described in detail below, including the audit programme and the handling of nonconformities.

Step by step

The process below shows what happens at each step, what the organisation provides and what the organisation receives.

Enquiry and application

The process begins with an enquiry and an application. In the application, the organisation provides information including the intended scope of certification, details of the organisation, the number of employees, processes and locations. Information on outsourced processes and any existing certifications is also included. This information forms the basis for DAI’s review of the application and for determining the audit time.

The organisation provides: a completed application with information on scope, organisation, processes and locations.

The organisation receives: confirmation of receipt of the application and any follow-up questions about the information.

Application review, audit time and quotation

DAI reviews the application to assess whether the information is sufficient and whether DAI has the competence and capacity to carry out the certification. The application is accepted or declined, and reasons are given for any refusal. At the same time, DAI determines the competences required of the audit team and of the person making the certification decision.

Audit time is determined in accordance with documented procedures. Factors include the requirements of the standard, the complexity of the organisation and its management system, the technological and regulatory context, outsourcing, the results of previous audits, size, the number of locations, risks, and whether audits are combined or integrated. Travel time is not included in the audit time. For ISO/IEC 27001, audit time is determined according to the specific criteria in ISO/IEC 27006-1.

The organisation receives: a quotation and agreement stating the scope and audit time.

Audit programme, audit team and audit plan

Once the agreement has been concluded, DAI prepares an audit programme for the full certification cycle. The programme sets out how all requirements of the standard are covered over the three years. The audit team is selected on the basis of the competences determined during the application review. The organisation is informed of the members of the audit team in sufficient time to object to any member.

Before each audit, the organisation receives an audit plan setting out the objectives, criteria, scope, schedule and composition of the audit team. The organisation provides: documentation in response to DAI’s document request and access to relevant persons and locations.

The organisation receives: an audit plan and information about the audit team.

Stage 1

Stage 1 (also called pre-audit at DAI) is the first part of the initial certification audit and is not a preliminary assessment or gap analysis. It reviews, among other things, the management system documentation and the scope, and whether the organisation is ready for stage 2. For ISO/IEC 27001, the Statement of Applicability is included in the review in accordance with ISO/IEC 27006-1. Stage 1 also evaluates whether internal audits and management review have been planned and performed, and whether the management system is implemented to an extent that shows the organisation is ready for stage 2.

DAI communicates the stage 1 conclusions to the organisation, including any issues that could be classified as nonconformities during stage 2. The interval between stage 1 and stage 2 is determined taking into account the organisation’s need to address the identified issues. The stage 1 results may lead to stage 2 being postponed or cancelled.

The organisation provides: the management system documentation and access to the persons who can explain the system.

The organisation receives: written conclusions from stage 1.

Stage 2

The purpose of stage 2 is to evaluate whether the management system is implemented and operating effectively. Stage 2 takes place at the organisation’s premises. The audit evaluates, among other things, conformity with all requirements of the standard, monitoring and measurement against objectives, the ability of the management system to meet statutory, regulatory and contractual requirements, operational control, internal audit and management review, and management responsibility for the policies. Certification is not in itself evidence that legal requirements are met.

The audit begins with an opening meeting and ends with a closing meeting, at which the audit team presents its conclusions and any nonconformities. For ISO/IEC 27001, the implementation of the controls included in the Statement of Applicability is audited.

The organisation provides: access to locations, persons, records and systems within the scope.

The organisation receives: an audit report.

Nonconformities and follow-up

If the audit team identifies nonconformities, they are classified as major or minor nonconformities. The organisation analyses the cause of each nonconformity and describes the correction and corrective actions. DAI assesses whether these are adequate and verifies their effectiveness.

DAI sets a deadline for addressing each nonconformity. The deadline is stated in the audit report. If implementation of corrections and corrective actions for a major nonconformity cannot be verified within six months of the last day of stage 2, a new stage 2 is conducted before certification can be recommended.

The organisation provides: root cause analysis, correction, corrective actions and evidence of implementation.

The organisation receives: DAI’s assessment of whether the nonconformities can be closed.

Certification decision and certificate

The certification decision is made by persons who did not carry out the audit themselves. Before the decision, DAI verifies that the information provided by the audit team is sufficient as a basis. Before the certificate is issued, correction and corrective actions for major nonconformities must have been reviewed, accepted and verified. Minor nonconformities must be closed, or DAI must have accepted an action plan for correction and corrective action, which is followed up at the next audit. Observations do not prevent the certificate from being issued.

The first three-year certification cycle begins on the date of the certification decision.

The organisation receives: notification of the decision and, if the decision is positive, a certificate that is valid for three years and states the certified scope.

Surveillance audits

Surveillance audits are conducted at least once each calendar year, except in the year of recertification. The first surveillance audit is conducted no later than 12 months after the date of the certification decision. All requirements are assessed during the cycle.

Surveillance audits cover, among other things, internal audit and management review, follow-up of nonconformities from the previous audit, handling of complaints, the effectiveness of the management system in relation to its objectives, progress of planned activities for continual improvement, continuing operational control, review of changes, and use of marks and references to certification.

Where nonconformities are identified, DAI sets a deadline for addressing them, which is stated in the audit report.

The organisation receives: an audit report and a decision on continued certification.

Recertification

The recertification audit is conducted in year 3 before the certificate expires. The audit evaluates the effectiveness of the management system as a whole in the light of internal and external changes, the continued commitment to effectiveness and improvement, and the contribution of the system to achieving the organisation’s objectives and intended results. Where there are significant changes to the organisation or the management system, recertification may require a stage 1.

Major nonconformities must be addressed and verified before the certification expires. After expiry, DAI can restore certification within six months, provided the outstanding recertification activities are completed. Otherwise, at least a stage 2 is required. From expiry until restoration, the organisation is not certified, and the expiry date of the new certificate follows the previous cycle.

The organisation receives: an audit report, a recertification decision and a new certificate for a new three-year period.

Changes, extension, suspension and withdrawal

Certification applies to the scope stated on the certificate. The organisation must inform DAI without delay of changes that may affect certification, such as changes in ownership, organisation, management, locations, scope or significant processes. DAI assesses whether the changes require audit activities.

An extension of scope requires a request, which DAI reviews to determine the necessary audit activities. The extension can be carried out together with a surveillance audit. The request is sent well in advance of the audit.

Certification may be suspended, among other things, when the management system has persistently or seriously failed to meet certification requirements, when the organisation does not allow surveillance or recertification audits to be conducted at the required frequency, or when the organisation itself requests it. During a suspension, the certificate is temporarily invalid and the organisation must not refer to the certification. DAI sets a deadline for resolving the issue, normally no more than six months. If this does not happen, certification is withdrawn or the scope is reduced to the parts that meet the requirements. The organisation is notified in writing of the decision and the reasons for it.

Impartiality and confidentiality

A certification body must be impartial. DAI does not provide consultancy on management systems and does not conduct internal audits for the organisations it certifies. The auditors report the issues identified and explain the content of the requirements of the standard, but do not prescribe solutions. Threats to impartiality are assessed on an ongoing basis.

Information that DAI receives about the organisation in connection with certification is treated as confidential.

Accredited and non-accredited certification

An accredited certification is carried out under an accreditation, where a national accreditation body (in Denmark, DANAK) has assessed that the certification body meets the requirements of the relevant standards for the certification scheme in question. A non-accredited certification is not covered by the assessment of the accreditation body.

As of November 2026, the standards have the following status:

StandardStatus
ISO/IEC 27001Covered by the DANAK accreditation. Accredited certificate.
ISO/IEC 27701Outside the accreditation. Non-accredited certificate.
ISO/IEC 42001Outside the accreditation. Non-accredited certificate.
ISO 22301Outside the accreditation. Non-accredited certificate.
IEC 62443Outside the accreditation. Non-accredited certificate.
ISO 9001Outside the accreditation. Non-accredited certificate.
ISO 14001Outside the accreditation. Non-accredited certificate.

Some customers, tenders and schemes require accredited certification. It is therefore relevant to know which requirements the certificate must meet for the recipient.

The process for IEC 62443 differs from the description on this page because the series is not a management system standard. The process is described on the page about IEC 62443.

Complaints and Appeals

Complaints about DAI’s activities are submitted via the complaint form. An organisation wishing to appeal a decision concerning certification, for example a refusal, a suspension or a withdrawal, submits the appeal via the appeal form. DAI acknowledges receipt in writing within five working days and handles complaints and appeals in accordance with a documented procedure. The person deciding on an appeal has not been involved in the decision under appeal. The outcome is communicated in writing with the reasons for it.

Use of certificate and certification mark

Organisations with a valid certificate from Dansk Audit Institut may refer to the certification and use DAI’s certificate logo in accordance with the rules in Use of certificates and certification marks, which form part of the certification agreement. The rules apply to both accredited and non-accredited certificates. DANAK’s accreditation mark may only be used in connection with certificates issued under accreditation (as of November 2026, certificates to ISO/IEC 27001). Use of marks and references to certification is reviewed during surveillance audits.

Frequently asked questions

How long does certification take?

The calendar time from agreement to certificate depends mainly on three factors: when stage 1 can be conducted, the interval between stage 1 and stage 2, and how quickly any nonconformities are addressed. The interval between stage 1 and stage 2 is determined on the basis of the organisation’s need to address the issues identified in stage 1. The certificate is issued only once the nonconformities have been addressed in accordance with the rules in step 7 and the certification decision has been made. If implementation of corrections and corrective actions for a major nonconformity cannot be verified within six months of the last day of stage 2, a new stage 2 is conducted. The number of audit days is stated in the quotation.

What determines the audit time?

Audit time is determined in accordance with documented procedures on the basis of factors such as the requirements of the standard, the size and complexity of the organisation, the number of locations, outsourcing, the technological and regulatory context, risks and the results of previous audits. Travel time is not included. For ISO/IEC 27001, the criteria in ISO/IEC 27006-1 apply. Audit time is the basis for the price in the quotation.

What is the difference between stage 1 and stage 2?

Stage 1 evaluates the documentation and scope and whether the organisation is ready for stage 2, and identifies issues that could become nonconformities. Stage 2 evaluates whether the management system is implemented and operating effectively in practice, and is conducted at the organisation’s premises.

What is a major and a minor nonconformity?

A major nonconformity is a nonconformity that affects the capability of the management system to achieve its intended results. A minor nonconformity is a nonconformity that does not affect this capability. Several minor nonconformities relating to the same requirement can together constitute a major nonconformity. Both types must be addressed within the deadline set by DAI. Before the certificate is issued, major nonconformities must be verified as closed, while for minor nonconformities DAI can accept an action plan (see step 7).

Can audits be conducted remotely?

Parts of an audit can be conducted using electronic means, such as video meetings and document sharing, when the evidence collected is sufficient. Stage 2 takes place at the organisation’s premises. The extent of remote activities is stated in the audit plan.

Can several standards be audited together?

Yes. Certification to several standards can be planned as one combined process. This is taken into account when determining the audit time, and the requirements of each standard are still assessed in full. Audit and certification to ISO/IEC 27001 are conducted and reported separately under the DANAK accreditation, and separate certificates are issued for each standard.

Can a certificate be transferred from another certification body?

A valid, accredited ISO/IEC 27001 certificate that is not suspended can be transferred in accordance with the international accreditation rules for transfer. DAI reviews the existing certification before a decision is made. For other standards, the process is determined case by case.

What happens if nonconformities are not closed?

For initial certification, no certificate is issued. If a major nonconformity cannot be verified as closed within six months of the last day of stage 2, a new stage 2 is conducted. During the certification period, failure to close nonconformities may lead to suspension, reduction of scope or withdrawal.

Samarbejde mellem kollegaer på kontoret

Send an enquiry

You can send an enquiry via the form on this page. Please state the intended scope, standard, number of employees, processes and locations. On the basis of this information, Dansk Audit Institut reviews the application, determines the audit time and sends a quotation. Questions can also be sent via the contact page.